Week of the August 19-24

We've been pretty busy this summer and last week was no exception our biggest project last week was a basement remodel in West Orange (on Harriet St)  we demo'ed , sheet-rocked, hung ceiling panels, changed doors, trimmed it out and painted we estimate it should take us two in half weeks to completed and as of today we are on track to finish on time or before.  Here is a small sample of what we have done:

We are also still working on our Hasbrouck Heights project lots to do there tiling, trimming, hanging cabinets, painting etc... and we also worked on a few paint jobs we painted a few rooms in Barnardsville, Basking Ridge and in Westfield.

Our bathroom project in Jefferson in on hold we are waiting for the homeowners to come back from vacation.